Project Introduction
Layout(Inbound floor area)
Outbound
Layout(Outbound platform area )
Inbound
Layout(Inbound floor area)
Outbound
Layout(Outbound floor area)
Project Features
Project Scale is large
BEST project budget is around RMB 200 Million super big project. As this system integrator ,it took 8 months for the whole project with the conveying line length at.
Switching steps are complicated
1. The construction process involved complex switching steps; 2. First construct new outbound area and disassemble old outbound after switch to new outbound; 3. Then construct new inbound matrix and complete the old and new inbound matrix switch; 4. Inbound cross belt switch; 5. The final detailed stages close.